Waste oil field fracturing fluid treatment device
Release time:2016-5-13 15:56:16   click:times   【Print】【close

         Fracturing fluid waste treatment facilities treatment technology with physical chemistry method of oxidation - air flotation - coagulation - filter is given priority to, the whole process is mainly divided into the following steps:

         The first step: the pretreatment of the fracturing fluid filtration and improve the system.
In fracturing fluid into the oxidation - air flotation - coagulation - filtration process before the Lord, to remove impurities in fracturing fluid, reduce subsequent machine jams, wear and ensure its processing efficiency. The process for setting fracturing fluid lift pump and filter pretreatment device for fracturing fluid preparation.

Step 2: tubular reactor for oxidation reaction.

         The pretreatment of fracturing fluid to tubular reactor, the preparation of medicine directly added to the tubular reactor for oxidation reaction.

Step 3: oil - water - mud separation

         In oil - water - mud waste separation facilities in fracturing fluid further oxidation, oil-water separation was achieved by air flotation, the top of the oil through the oil removal - chain scraper machine to scrape the oil collecting tank. By the coagulation sedimentation process of the fracturing fluid gel, solid phase separation of components.

Step 4: filtration system

         From the separator in the middle of sewage in turn after a filtering tank and secondary filtering tank of further filtration separation treatment of sewage.

Step 5: the sludge treatment
          
         Coagulation after the solid slag, mud deposition in oil - water - mud at the bottom of the separator, periodically from the separator at the bottom of the further enrichment in sludge storage tanks.
The process consists of pretreatment, tubular reactor, coarse separator, sludge treatment, a filter, secondary filter, water boxes and other units.